I’ve taken a look at the July 28, 2009 WRE Kauai 22.5 LLC Bio Fuels and Biomass Generator Proposal. Below are my thoughts. The
“WRE Kauai 22.5 LLC” document is without any doubt the least
informative, least-professional and most-poorly written project
proposal that I have encountered during my 25+ years in the electric
power industry. I have given much consideration to that statement and
do not make it lightly, nor do I write it with any intent to be
insulting to anyone... but there is simply no other way to state it, as
the contrast between this proposal and every other proposal I have
reviewed - for any type of product or service - is so stark.
The
document provides a minimal amount of information about the proposed
project, includes absolutely no substantive information about the past
or ongoing performance of the technology or the past or ongoing
performance of the companies involved, and includes absolutely no
information about the credentials, experience or accomplishments of the
principals.
What precisely is the project?
As
near as I can tell, once one separates the extraneous from the
substance, it is a proposal to build three 7.5 MW combustion units.
(Actually, because a large portion - 2.5 MW - of the output would be
used for station power and the private “Fast Grow Greenhouse” owned by
the project owners, the average delivered power to KIUC is more like
6.7 MW net, for a total of 20 MW.)
From
what the proposal says, the project would be baseload (the proposal’s
words) and appears to lack the dispatchability that would enable KIUC
to more readily accommodate the integration of more intermittent
resources, such as solar, wind, and demand-side management, into the
grid. (In my opinion, dispatchability is a very important attribute for
KIUC resource acquisitions.) From what I could tell, the proposal seems
to imply that KIUC must schedule the full output of 1 or 2 units
off-peak and the full output of 2 or 3 units on-peak.
The
fuel would be imported from the Pacific Northwest, and would comprise
91% wood products and 9% plastics and other materials. The fuel supply
is purported to be renewable, but there is nothing in the proposal to
indicate that it has actually received such certification, or that any
official accreditation body has acknowledged that either the project or
the fuel would be entitled to Renewable Energy Attributes.
The
project sponsors have not accomplished anything (at least from what is
written in the document) to date regarding site acquisition,
certification of the green attributes of the concept, or any of the
other basics that a project developer would normally bring to the table.
So
what we have here is apparently a 20 MW, limited dispatchability,
wood/plastic-burning power plant that might or might not qualify as a
renewable project. Nothing too exceptional so far... Unfortunately,
beyond that, it’s all unknown, unstated, or hand-waving.
Here are some important questions that should have been answered by the proposal:
The technology:
where has a 7 MW power plant, burning this particular fuel, built by
this company, using exactly the technology that is being proposed, been
in operation for any length of time, providing its output to an
electric utility? With whom could one speak to verify technical and
contractual performance and ask other questions?
The technology:
although it is not directly relevant to KIUC (because the project owner
would own the “Fast Grow Greenhouse” that receives the CO2 from the
plant), it still is important to the overall financial and technical
viability of the proposal to know: where has this Fast Grow Greenhouse
been implemented as part of such a project? With whom could one speak
to verify technical and contractual performance and ask other questions?
The technology for the fuel supply:
although it is not directly relevant to KIUC (because the project owner
would be responsible for constructing, owning and operate the “CT Fuel”
CarbonTech solid biofuel conversion facility in the Pacific Northwest),
it is still important to the overall project viability: where has this
type of facility been operating, for how long, as part of what
utility-scale project? With whom could one speak to verify technical
performance and ask other questions?
The long-term security of the fuel source:
the proposed project would require 3.6 million tons of fuel over 20
years. Do the project sponsors have either the physical or financial
options lined up for that much fuel? Are they willing to provide
performance bonds or other means to acquire such options so if the
project sponsors go belly-up a few years after operations begin, KIUC
won’t find itself without a viable resource to meet its customers’
demand? (Including proposals with some lumber mills in the Pacific
Northwest, as was done in the proposal, gives me no confidence
whatsoever, when considered in light of the apparent lack of experience
and depth of the project owners. It’s not as if Bechtel or Shell is
backing up the proposal.). In other words, what do the project sponsors
propose to ensure to KIUC that there will indeed be a 20 year supply of fuel?
The renewable attributes of the resource:
where to date has this CTFuel source been certified as eligible for
REAs, and by what credible accreditation agency? (There is really
nothing in the proposal that assures me that the project would not
ultimately entail anything other than using up fuel that is already in
the forest. It isn’t clear to me that chopping down forests in the
northwest - or the Amazon or anywhere else - is “renewable” unless the
trees are replanted and reharvested in an ongoing cycle. But that is
not my call - it’s the call of an industry-recognized REA accreditation
agency.) With what organization(s) have the project sponsors worked to
ensure that their proposed REAs are indeed legitimate, will not be
double-counted, will be properly accounted, etc.? Why haven’t the
project sponsors already handled this, versus claiming that “we will go
to the Hawaii Energy Commission in the future?” In my opinion, the
question of the REA certification of CT Fuel should have been addressed
before the project proponents even walked in the door. (Leaving that
key matter unaddressed is no way to market a new technology, in my
book.)
The product:
what, in greater detail, is the proposal offering? For example, the
proposal states that it offers “Economy Base Load Energy, delivered all
hours.” Is the project really offering non-firm energy (that’s what
economy energy is), making no contribution to KIUC’s capacity
requirements or reliability needs? How much flexibility would KIUC have
over the output of the three units? (Is it all-or-none? Is there a
minimum load? Are there ramping constraints? etc.) In other words, more
information is needed about the operating characteristics of the
proposed boiler/turbine/generator.
Emissions:
The proposal claims that there would be negligible emissions of
hazardous pollutants. I do not have the expertise to comment on those
claims... but in my gut I am somewhat skeptical, particularly in light
of burning plastics. This is an issue for someone else to look into.
(Also, I note that page 22 compares emissions to coal and raw wood,
rather than to the fuels used by KIUC. Not very relevant.)
The financial credibility of the project over its lifetime:
If the project owners do not have substantial capital of their own
invested in the project, there is little to keep them from walking away
from the project if future market conditions result in future operating
costs that exceed future operating revenues. The proposal says that
Kauai 22.5 intends to use tax credits... it will package ITCs with a
KIUC Power Purchase Agreement as security for capital equity and
loan... it will use production tax credits as security for working
cash... How much real investor capital is involved, as opposed to
leveraging against tax credits and KIUC’s financial credibility? How
highly leveraged is the project? It is a very bad omen if the
developers have little or no skin in the game, particularly when one
considers all of the other warning flags regarding credibility (some of
which I will list below). What guarantees will be provided that in year
n+1, if the project owners’ costs escalate for any number of reasons,
so that the plant would be operating at a loss (after having been
operating at a profit during years 1 through n), the project owners
will continue to perform?
The financial credibility of the project owners:
There are many issues related to default that need to be addressed when
any business wants another business (such as KIUC) to enter into a
long-term contract. What if the project owners do not perform? What are
will be the consequences to them, versus simply walking away from a
project that is highly leveraged (see #8 above). What if they simply
close up shop? Where does KIUC obtain the replacement capacity on short
notice? Are there significantly high penalties for non-performance, and
more importantly, would the project owners have enough investment and
equity (vs. leveraging tax credits) to actually pay for such
non-performance? Alternatively: are banks or other institutions willing
to ensure payment through performance bonds? What if the project owners
cause damage or injury? If they are not sufficiently-capitalized, KIUC
and its customers will be the deep pockets in any lawsuit. These are
especially important issues in this case, where it appears (from the
limited information provided in the proposal) that the developers’
corporate office could simply be a rented room above a strip mall in
Arizona.
The pricing arrangement:
While I recognize that the actual numbers would be subject to
negotiation and to some extent should be confidential at this time,
there are still some basics regarding the structure of the desired
pricing arrangement that should be presented. So while I do not fault
the proposal for containing no specific prices, I am concerned that
what little information is provided is unclear. On the one hand, the
proposal refers to a 20-year term that includes a 1% annual escalator
in the pricing. On the other hand, the proposal says that prices will
not increase during the first year, implying that future years are not
set by the 1% escalator, but by other factors. Which is it? As to
structure of the pricing: do the developers propose level payments
(that would increase by 1% per year) that would exceed either the
developers’ marginal operating costs or KIUC’s avoided energy costs in
the early years of the contract? That type of payment structure could
backfire on KIUC in later years if inflation drives up operating costs
so that the KIUC payments in later years became less than the
developers’ operating costs in those years. (In that case, unless KIUC
insisted on a large performance bond or escrow account, the developers
could simply abandon the project, leaving KIUC in the lurch.)
There
are certainly a number of other questions, but those are some of the
biggest ones. And beyond that, there is the question of the developers’
credibility, experience, competence, and ability to deliver. There are
a lot of yellow and/or red flags:
The
writers of the proposal show little knowledge of the technical field
and/or the jargon of the power industry. They misuse the concepts of
“efficiency,” the term “negawatts” (which they call power consumed
within the plant; the conventional definition of negawatts is power
saved by measures taken to reduce consumption), and the concept of
economy energy. The proposal states that there is no need for an
interconnection study if the project is connected to a KIUC substation,
when there are clearly numerous interconnection-related issues that
virtually always need to be studied, even in such an instance. Etc.,
etc.
- The
proposal is plagued by lack of attention to detail: there are numerous
misuses of MW vs. MWH; there are errors in stating the deliveries for
days vs years, and there are errors in tons of fuel per hour vs. tons
of fuel per day; there is lack of attention to detail in tables (the
same number of MWHs are delivered in 28 day months as in 31 day
months); there are no page numbers; there is no table of contents or
structure to the proposal... Each of these is individually minor, but
cumulatively such lack of attention to detail is disturbing, and
particularly so in a proposal to a potential client by an unknown
entity with no track record: it does not instill any confidence as to
the competence of the project sponsors, the quality of the product, or
the commitment to doing the job right. Again, while this might seem
like nit-picking, I believe these are little signs are of extra
importance when dealing with entities that have made no attempts to
illuminate their credentials or experiences, and have provided no
references. So what else is left as a basis for judging the
capabilities of the project sponsors.
- Even
some of the most basic knowledge of the elements of contracts seems to
be lacking in the proposal. The lengthy so-called “Amendments to the
Proposal” are just attachments, not amendments.
So-called Amendment 1, supposedly about CT Fuel, provides little
meaningful data on CT Fuel - much of the information is generic
information about biomass; and while I do not know anything about the
credibility of the analytical labs used, they seem like
less-than-noteworthy labs. “Amendment” 2 is also irrelevant: it
comprises just generic articles on biocrops and has little to do with
the proposal itself.
Track Record / Credentials of Project Sponsors
There
is no information about the project financing or the backers of the
proposed project. To the contrary, here are the different entities
mentioned in the proposal:
CarbonTech Integrated Cooperative Companies
CarbonTech Cooperative
Clearstream Technologies
WRE Investor Group
Western Renewable Energy
Mountain Country Co Generation Inc (MCCG)
KMW Engineering
I
urge you to google them. Please let me know if you find any credible
references to any of them... I did not find any (although my time
limited the depth of my search). That’s strange. It is also strange
that while the proposal claims that “MCCG/KMW team has an international
reputation... it has built over 100 operating biomass combustion
facilities in North America since 1963,” the proposal did not include
any specific references to any biomass combustion power plants or their
owners.
Here are the names of the individuals mentioned in the proposal:
Steve Hall, Kauai 22.5 LLC, Show Low AZ, steve@westernrenewables.com
Robert Hennkens, Kauai 22.5 LLC, Tucson AZ, rhennkens@gmail.com
Doug Fant, Phoenix AZ, dsfant@gowebway.com
Dennis Ryan, Swanville MN, morgancreekfinance@gmail.com
Gmail.com,
gowebway.com: these do not seam like solid, professional email
addresses for principals in a company that wants to be a counter-party
to multi-million dollar contracts! Westernrenewables.com: go to that
website... let me know if you find anything of substance there?
All
minor things, one might argue. But what else is there to go by, since
overall, there is nothing in the proposal that instills any confidence
that there is any track record on the part of the individuals or the
companies involved? (Note: I can not say that there is not such a track
record; but it is extremely unusual that if such a record existed, it
would not have been a part of the proposal.)
The proposal seems to attempt to imply some credibility/substance/experience by including:
On
page 13: a map with purported CT Fuel mills in Washington. That needs
investigation... they could just be pulp processing yards by another
name. And what contractual relationship exists to the project sponsors?
On
pages 14-16: a 2005 proposal by EFS Bio Energy West Generation LLC
(note: I found no credible google references to this company) to buy
wood chips. (By the way, the photo looks like a lumberyard - if the
source of this “renewable fuel” is from thinning forests, is that
really a “perpetually” renewable resource? It seems not much different
than consuming a resource like oil, unless a part of the process is
replanting as much as is cut down. Or is this just another biomass scam
like corn ethanol?) The proposal on these pages does not demonstrate
any experience as part of an operating power plant project. Other names
on this sample: EFS Clearstream Technologies (no google references);
westernrenewablefuels.com (I did not find anything showing its
existence on the web)
On
p17: A 2006 letter expressing interest in building a cogen plant in
Washington. A letter of interest? Big deal and of no consequence... Did
it get built? What has been its operating experience?
If
these are the strongest indicators of experience that the project
sponsors could provide in the proposal, that is another big warning as
to the real substance of their experience.
The
above are some of the reasons why I am skeptical and harbor the
suspicion that this could at best be either a tremendously risky
venture (in which KIUC and its customers would bear the risk), and at
worst, a giant con job. My concerns are not allayed by the inclusion of
all of the politically-correct hand-waving about renewables and the use
of ludicrous phrases like “will perpetually maintain 90 days of fuel supply” and “perpetual
family jobs.” It all seems like language intended to divert the
reader’s attention from the lack of substance in the document.
______________________
Based
on all of the above, my experience and intuition say: walk away from
this proposal as quickly as possible. But, what if this is just a
poorly written proposal that did a very bad job of presenting a very
good project? (Not very likely... but anything’s possible.) In that
case, if I were responsible for reviewing projects and my boss ordered
me to give this another look, to forget about what has already been
sent out and start fresh with a clean slate, then the first thing I
would want is all of the information that I outlined above (actually, a
lot more, if it was really my job and I was being paid to diligently
evaluate potential multi-million dollar contracts).
But
first: I want to state that none of what I outlined above remotely
qualifies as “confidential information,” and no confidentiality
agreement should be required by the recipient of such information. In
fact, if I was asked to sign any agreement of any type with anyone
before receiving and evaluating the information above, I would just
walk away from the entire proposal. (Among other things, scam artists
can use confidentiality agreements - which really are only appropriate
in the later stages of negotiations - as “evidence” in nuisance suits
in which they claim that they were led on by the recipient of the
proposal and were forced to invest time and energy on the proposal, and
are therefore entitled to some compensation.) In addition, I would never
sign any sort of confidentiality agreement before first ascertaining
the credibility - by speaking with a number of references - of the
other party. The other party’s track record is not confidential, and absolutely must be provided before even considering any confidential discussions.
Second:
while the information that I outlined above might seem to be somewhat
more than might be reasonable to require in an initial proposal, I
believe that it is reasonable in light of the lack of demonstrated
experience of the project sponsors and their technology. Yes, the
hurdle is indeed somewhat higher for start-up companies than for
companies with established track records. And that’s the way it should
be. Failure to recognize that basic principle was one of the causes of
the dot.com bubble, to the dismay of investors and dreamers who did not
exercise due diligence.
And
lastly: everything that I wrote above was based solely on the document
that was provided to me. I could not judge the credentials,
capabilities or integrity of the parties who drafted the proposal based
solely on the document that was provided. Therefore, I have not done
so, and I do not want you to walk away from this review thinking that I
have done so. Rather, I have only expressed my skepticism based on an
informed reading of the document, my experience, and the caution that I
would use if I was asked to invest my own money (and come to think of
it, since KIUC is a coop, it is my own money).
I hope that these thoughts were of some help to you.
Carl Imparato